Road Construction As of 7/23/2021

I-39/90 and I-43/WIS 81 interchange area reconstruction, Beloit
Illinois state line to Hart Road | County X/Hart Road to Freeman Parkway
Anticipated construction completion: November 2021

  • Updated: SHORT-TERM RAMP CLOSURE: The I-43/WIS 81 ramp to I-39/90 northbound is CLOSED until Friday, July 30.
    • Drivers must use alternate routes, such as I-43 to Hart Road then Shopiere Road to the northbound Interstate.
    • Crews will pave concrete connections for the new configuration of WIS 81 through the Diverging Diamond Interchange.
    • On Friday, July 30, I-43 southbound traffic will be shifted to the new WIS 81 Diverging Diamond Interchange (DDI) pavement. This temporary configuration will allow I-43 southbound motorists to access I-39/90 southbound or the city of Beloit. At this time, I-43 southbound motorists will also be able to use the new WIS 81 interchange ramp to I-39/90 northbound.
    • I-43 northbound motorists will continue to use the detour route to reach I-39/90 northbound.
  • I-39/90 traffic located on new concrete pavement between the Hart Road and Cranston Road overpasses.
    • Use Exit 185 to access I-43 or WIS 81/Milwaukee Road. Ramps and crossroad traffic are controlled by traffic signals.
  • I-43 traffic is located on the new WIS 81 lanes between I-39/90 and Gateway Blvd. Reduced speed limits from Hart Road to Beloit.
    • One lane remains OPEN each way. Watch for lane shifts and crossovers.
    • Be alert for construction equipment as bridge construction is taking place within the interchange area.
  • All WIS 81/Milwaukee Road traffic is shifted onto the eastbound side between Cranston Road and the Ford Street/Freeman Parkway intersection.
    • Eastbound (outbound) WIS 81/Milwaukee Road is reduced to one lane within these limits. Plan ahead for backups and delays.
    • Two lanes remain open on westbound (inbound) WIS 81/Milwaukee Road.
    • Access remains OPEN to local businesses.
  • Gateway Boulevard is reduced to one lane in each direction from S. Turtle Town Hall Road west to the railroad tracks.
    • Access is maintained to local businesses, including Kerry Corporation.
    • Traffic configuration in effect until August 2021.

Road Construction Updates on the Entire Project:

Go to the website for the Wisconsin Department of Transportation and the I-39/90 Project Team at www.i39-90.wi.gov or follow them on Facebook at www.facebook.com/WisconsinI3990Project.